Time and Work Questions Answers
-
15. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C
- Rs. 300
- Rs. 400
- Rs. 500
- Rs. 600
Answer And Explanation
Answer: Option B
Explanation:
C's 1 day's work =
\begin{aligned}
\frac{1}{3}- \left(\frac{1}{6} +\frac{1}{8} \right) \\
=\left(\frac{1}{3} - \frac{7}{24} \right) \\
= \frac{1}{24} \\
A:B:C = \frac{1}{6}:\frac{1}{8}:\frac{1}{24} \\
= 4:3:1 \\
C's Share = \frac{1}{8}* 3200 \\
= 400
\end{aligned}
If you are confused how we multiplied 1/8, then please study ratio and proportion chapter, for small information, it is the C ratio divided by total ratio. -
16. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?
- 30 days
- 40 days
- 50 days
- 60 days
Answer And Explanation
Answer: Option B
Explanation:
Let 1 man's 1 day work = x
and 1 woman's 1 days work = y.
Then, 4x + 6y = 1/8
and 3x+7y = 1/10
solving, we get y = 1/400 [means work done by a woman in 1 day]
10 women 1 day work = 10/400 = 1/40
10 women will finish the work in 40 days -
17. A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ?
- 3 days
- 4 days
- 5 days
- 6 days
Answer And Explanation
Answer: Option A
Explanation:
To calculate the answer we need to get 1 man per day work and 1 woman per day work.
Let 1 man 1 day work =x
and 1 woman 1 days work = y.
=> 6x+5y = 1/6
and 3x+4y = 1/10
On solving, we get x = 1/54 and y = 1/90
(9 men + 15 women)'s 1 days work =
(9/54) + (15/90) = 1/3
9 men and 15 women will finish the work in 3 days
-
18. A can do a certain job in 25 days which B alone can do in 20 days. A started the work and was joined by B after 10 days. The number of days taken in completing the wotk were ?
- \begin{aligned} 14\frac{2}{3}kmph \end{aligned}
- \begin{aligned} 15\frac{2}{3}kmph \end{aligned}
- \begin{aligned} 16\frac{2}{3}kmph \end{aligned}
- \begin{aligned} 17\frac{2}{3}kmph \end{aligned}
Answer And Explanation
Answer: Option C
Explanation:
Work done by A in l0 days = (1/25) *10 = 2/5
Remaining work = 1 - (2/5) = 3/5
(A+B)s 1 days work = (1/25) + (1/20) = 9/100
9/100 work is done by them in 1 day.
hence 3/5 work will be done by them in (3/5)*(100/9)
= 20/3days.
Total time taken = (10 + 20/3) = 16*(2/3) days -
19. 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
- 6 days
- 7 days
- 8 days
- 9 days
Answer And Explanation
Answer: Option B
Explanation:
1 woman's 1 day's work = 1/70
1 Child's 1 day's work = 1/140
5 Women and 10 children 1 day work =
\begin{aligned}
\left(\frac{5}{70}+\frac{10}{140}\right) \\
= \frac{1}{7}
\end{aligned}
So 5 women and 10 children will finish the work in 7 days. -
20. A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in
- \begin{aligned} 13\frac{1}{4} \end{aligned}
- \begin{aligned} 13\frac{1}{2} \end{aligned}
- \begin{aligned} 13\frac{3}{4} \end{aligned}
- \begin{aligned} 13\frac{4}{4} \end{aligned}
Answer And Explanation
Answer: Option C
Explanation:
A's 1 day work = 1/16
B's 1 day work = 1/12
As they are working on alternate day's
So their 2 days work = (1/16)+(1/12)
= 7/48
[here is a small technique, Total work done will be 1, right, then multiply numerator till denominator, as 7*6 = 42, 7*7 = 49, as 7*7 is more than 48, so we will consider 7*6, means 6 pairs ]
Work done in 6 pairs = 6*(7/48) = 7/8
Remaining work = 1-7/8 = 1/8
On 13th day it will A turn,
then remaining work = (1/8)-(1/16) = 1/16
On 14th day it is B turn,
1/12 work done by B in 1 day
1/16 work will be done in (12*1/16) = 3/4 day
So total days =
\begin{aligned} 13\frac{3}{4} \end{aligned}
It may be a bit typical question, but if are not getting it in first try then give it a second try. Even not, then comment for explanation for this. We will be happy to help you.
-
21. 5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio
- 1:2
- 1:3
- 2:1
- 2:3
Answer And Explanation
Answer: Option C
Explanation:
Let 1 man 1 day work = x
1 boy 1 day work = y
then 5x + 2y = 4(x+y)
=> x = 2y
=> x/y = 2/1
=> x:y = 2:1