Processing math: 100%
download Mastguru Android App

Time and Work Questions Answers

  • 8. A can do a job in 16 days, B can do same job in 12 days. With the help of C they did the job in 4 days. C alone can do the same job in how many days ?

    1. 612days
    2. 712days
    3. 835days
    4. 935days
    Answer And Explanation

    Answer: Option D

    Explanation:

    In this question we having, A's work, B's work and A+B+C work. We need to calculate C's work.
    We can do it by,
    (A+B+C)'s work - (A's work + B's work).

    Let's solve it now:

    C's 1 day work =
    14(116+112)=(14748)=548

    So C can alone finish the job in 48/5 days,
    Which is =
    935days

  • 9. To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take

    1. 24 days
    2. 16 days
    3. 12 days
    4. 8 days
    Answer And Explanation

    Answer: Option D

    Explanation:

    A+B 1 day work = 1/8
    B+C 1 day work = 1/12
    A+B+C 1 day work = 1/6

    We can get A work by (A+B+C)-(B+C)
    And C by (A+B+C)-(A+B)

    So A 1 day work =
    16112=112

    Similarly C 1 day work =
    1618=4324=124

    So A and C 1 day work =

    112+124=324=18

    So A and C can together do this work in 8 days

  • 10. A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it

    1. 40 days
    2. 35 days
    3. 30 days
    4. 25 days
    Answer And Explanation

    Answer: Option C

    Explanation:

    Suppose B takes x dáys to do the work.
    As per question A will take
    234x=3x2days

    (A+B)s 1 days work= 1/18
    1/x + 2/3x = 1/18 or x = 30 days

  • 11. A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. B alone can do the whole work in

    1. 15 days
    2. 10 days
    3. 9 days
    4. 8 days
    Answer And Explanation

    Answer: Option A

    Explanation:

    Ratio of times taken by A and B = 1:3
    Means B will take 3 times which A will do in 1 time

    If difference of time is 2 days, B takes 3 days
    If difference of time is 10 days, B takes (3/2) * 10 =15 days

  • 12. A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in

    1. 5 days
    2. 6 days
    3. 7.5 days
    4. 8.5 days
    Answer And Explanation

    Answer: Option C

    Explanation:

    B's 5 days work =
    1105=12Remaining work =112=12A can finish work =1512=7.5days

  • 13. A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. In how many hours B can complete the work ?

    1. 10 hours
    2. 12 hours
    3. 16 hours
    4. 18 hours
    Answer And Explanation

    Answer: Option B

    Explanation:

    Work done by A in 1 hour = 1/4

    Work done by B and C in 1 hour = 1/3

    Work done by A and C in 1 hour = 1/2

    Work done by A,B and C in 1 hour = (1/4)+(1/3) = 7/12

    Work done by B in 1 hour = (7/12)–(1/2) = 1/12

    => B alone can complete the work in 12 hour

  • 14. A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?

    1. 3512
    2. 3612
    3. 3712
    4. 3812
    Answer And Explanation

    Answer: Option C

    Explanation:

    Work done by A in 20 days = 80/100 = 8/10 = 4/5

    Work done by A in 1 day = (4/5) / 20 = 4/100 = 1/25 --- (1)

    Work done by A and B in 3 days = 20/100 = 1/5 (Because remaining 20% is done in 3 days by A and B)

    Work done by A and B in 1 day = 1/15 ---(2)

    Work done by B in 1 day = 1/15 – 1/25 = 2/75

    => B can complete the work in 75/2 days = 37 (1/2) days

Post a comment