Question Detail
If the cost of x metres of wire is d rupees, then what is the cost of y metres of wire at the same rate ?
- xd
- yd
- yd/x
- x/yd
Answer: Option C
1. If the cost of x metres of wire is d rupees, then what is the cost of y metres of wire at the same rate ?
- xd
- yd
- yd/x
- x/yd
Answer: Option C
2. 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work ?
- 24 days
- 28 days
- 34 days
- 35 days
Answer: Option A
Explanation:
Less Men, means more Days {Indirect Proportion}
Let the number of days be x
then,
27 : 36 :: 18 : x
[Please pay attention, we have written 27 : 36 rather than 36 : 27, in indirect proportion, if you get it then chain rule is clear to you :)]
\begin{aligned}
x = \frac{36*18}{27} \\
x = 24
\end{aligned}
So 24 days will be required to get work done by 27 men.
3. 4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat weavers in 8 days ?
- 12
- 14
- 16
- 18
Answer: Option C
Explanation:
Please always remember, that what exactly we need to calculate before applying chain formula. As in this question we need to find how many mats, RIGHT !
So we will compare everything with "number of mats"
As,
More men, More number of mats (Direct Proportion)
More days, More number of mats (Direct Proportion)
So, it can be solved as,
\begin{aligned}
\begin{bmatrix}Weavers & 4 & 8 \\Days & 4 & 8 \end{bmatrix} :: 4 : x \\
=> x*4*4 = 8*8*4 \\
=> x = 16
\end{aligned}
4. An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metre of cloth ?
- 194 seconds
- 195 seconds
- 196 seconds
- 197 seconds
Answer: Option B
Explanation:
Let the time required by x seconds.
Then, More cloth means More time (Direct Proportion)
So,
\begin{aligned}
0.128 : 1 :: 25 : x
=> x = \frac{25*1}{0.128} \\
=> x = 195.31
\end{aligned}
So time will be approx 195 seconds
5. In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, how many men will be catered to with the remaining meal ?
- 38 men
- 32 men
- 34 men
- 30 men
Answer: Option D
Explanation:
There is meal for 200 children. 150 children have taken the meal.
Remaining meal is to be catered to 50 children.
Now, 200 children = 120 men
So, 50 Children = 120/200 * 50 = 30 men