A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ?

  • 3 days
  • 4 days
  • 5 days
  • 6 days
Similar Questions :

1. A does a work in 10 days and B does the same work in 15 days. In how many days they together will do the same work ?

  • 5 days
  • 6 days
  • 7 days
  • 8 days

2. A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days

3. 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?

  • 6 days
  • 7 days
  • 8 days
  • 9 days

4. A tyre has two punctures. The first puncture alone would have made the tyre flat in 9 minutes and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how long does it take both the punctures together to make it flat ?

  • \begin{aligned} 3\frac{1}{5} min \end{aligned}
  • \begin{aligned} 3\frac{2}{5} min \end{aligned}
  • \begin{aligned} 3\frac{3}{5} min \end{aligned}
  • \begin{aligned} 3\frac{4}{5} min \end{aligned}

5. A man can do a piece of work in 5 days, but with the help of his son he can do it in 3 days. In what time can the son do it alone ?

  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 5\frac{1}{2}days \end{aligned}
  • \begin{aligned} 4\frac{1}{2}days \end{aligned}
Read more from - Time and Work Questions Answers