A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it
- 40 days
- 35 days
- 30 days
- 25 days
Answer: Option C
Explanation:
Suppose B takes x dáys to do the work.
As per question A will take
\begin{aligned}
2* \frac{3}{4} * x = \frac{3x}{2}days
\end{aligned}
(A+B)s 1 days work= 1/18
1/x + 2/3x = 1/18 or x = 30 days