A does a work in 10 days and B does the same work in 15 days. In how many days they together will do the same work ?

  • 5 days
  • 6 days
  • 7 days
  • 8 days
Similar Questions :

1. A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?

  • 3512
  • 3612
  • 3712
  • 3812

2. A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in

  • 1314
  • 1312
  • 1334
  • 1344

3. Worker A takes 8 hours to do a job. Worker B takes 10 hours to do a job. How long should it take both A and B, working together to do same job.

  • 49
  • 249
  • 349
  • 449

4. A is twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work.

  • 27 days
  • 54 days
  • 56 days
  • 68 days

5. A can do a certain job in 25 days which B alone can do in 20 days. A started the work and was joined by B after 10 days. The number of days taken in completing the wotk were ?

  • 1423kmph
  • 1523kmph
  • 1623kmph
  • 1723kmph
Read more from - Time and Work Questions Answers
Post a comment

  • Sujith 8 years ago

    one pump can fill a tank in 4 hrs another will vacate in 5 hrs. In what time will the tank be filled when both the pumps work simultaneously?