Question Detail

A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. In how many hours B can complete the work ?

  • 10 hours
  • 12 hours
  • 16 hours
  • 18 hours
Similar Questions :

1. A can finish a work in 18 days and B can do same work in half the time taken by A. then working together, what part of same work they can finish in a day

  • 1\5
  • 1\6
  • 1\7
  • 1\8

2. Rahul and Sham together can complete a task in 35 days, but Rahul alone can complete same work in 60 days. Calculate in how many days Sham can complete this work ?

  • 84 days
  • 82 days
  • 76 days
  • 68 days

3. 5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio

  • 1:2
  • 1:3
  • 2:1
  • 2:3

4. Worker A takes 8 hours to do a job. Worker B takes 10 hours to do a job. How long should it take both A and B, working together to do same job.

  • \begin{aligned} \frac{4}{9} \end{aligned}
  • \begin{aligned} 2\frac{4}{9} \end{aligned}
  • \begin{aligned} 3\frac{4}{9} \end{aligned}
  • \begin{aligned} 4\frac{4}{9} \end{aligned}

5. A can do a job in 16 days, B can do same job in 12 days. With the help of C they did the job in 4 days. C alone can do the same job in how many days ?

  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 8\frac{3}{5}days \end{aligned}
  • \begin{aligned} 9\frac{3}{5}days \end{aligned}
Read more from - Time and Work Questions Answers