- Home
- Quantitative
- English
- Reasoning
- IT Officer
- Programming
-
Computer
- Computer Awareness Questions Answers - Set 1
- Computer Awareness Questions Answers - Set 2
- Important Abbreviations Computer Awareness Questions Answers
- Important File Extensions Questions Answers
- Computer System Architecture Questions Answers
- MS Office Questions Answers
- MS Excel Questions Answers
- MS PowerPoint Questions Answers
-
GK
- Geography Questions Answers
- Indian History Questions Answers
- World History Questions Answers
- Indian Economy Questions Answers
- Indian Polity and Constitution
- Physics Questions Answers
- Chemistry Questions Answers
- Biology Questions Answers
- First In India
- First In World
- Longest and Largest
- Books and Authors
- Important Days of year
- Countries and Capitals
- Inventions and Inventors
-
Current Affairs
- Current Affairs
- Current Affairs 2018
- Current Affairs 2018 - 2019 PDF
- Current Affairs August 2019
- Current Affairs July 2019
- Current Affairs June 2019
- Current Affairs May 2019
- Current Affairs April 2019
- Current Affairs March 2019
- Current Affairs February 2019
- Current Affairs January 2019
- Current Affairs December 2018
- Current Affairs November 2018
- Current Affairs October 2018
- Current Affairs September 2018
- Govt Jobs
- Exams
- Online Quiz
- You are here
- Home
- Quantitative Aptitude
- Arithmetic Aptitude Questions Answers
- Time and Work Questions Answers
- Aptitude Question
- Current Affairs 2019
- Current Affairs 2018
- Current Affairs December 2018
- Current Affairs November 2018
- Current Affairs October 2018
- Current Affairs September 2018
- Current Affairs August 2018
- Current Affairs July 2018
- Current Affairs June 2018
- Current Affairs May 2018
- Current Affairs April 2018
- Current Affairs March 2018
- Current Affairs February 2018
- Current Affairs January 2018
- Current Affairs 2018
- Current Affairs PDF
- Current Affairs PDF Download
- Current Affairs July 2019 PDF
- Current Affairs June 2019 PDF
- Current Affairs May 2019 PDF
- Current Affairs April 2019 PDF
- Current Affairs March 2019 PDF
- Current Affairs February 2019 PDF
- Current Affairs January 2019 PDF
- Current Affairs December 2018 PDF
- Current Affairs November 2018 PDF
- Current Affairs October 2018 PDF
- Current Affairs September 2018 PDF
- Current Affairs August 2018 PDF
- Current Affairs July 2018 PDF
- Current Affairs June 2018 PDF
- Current Affairs May 2018 PDF
- Current Affairs April 2018 PDF
- Current Affairs March 2018 PDF
- Current Affairs February 2018 PDF
- Current Affairs January 2018 PDF
Question Detail
A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in
- 5 days
- 6 days
- 7.5 days
- 8.5 days
Answer: Option C
Explanation:
B's 5 days work =
\begin{aligned}
\frac{1}{10}*5 = \frac{1}{2} \\
\text{Remaining work =} 1-\frac{1}{2} \\
= \frac{1}{2} \\
\text{A can finish work =}15*\frac{1}{2} \\
= 7.5 days
\end{aligned}
1. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C
- Rs. 300
- Rs. 400
- Rs. 500
- Rs. 600
Answer: Option B
Explanation:
C's 1 day's work =
\begin{aligned}
\frac{1}{3}- \left(\frac{1}{6} +\frac{1}{8} \right) \\
=\left(\frac{1}{3} - \frac{7}{24} \right) \\
= \frac{1}{24} \\
A:B:C = \frac{1}{6}:\frac{1}{8}:\frac{1}{24} \\
= 4:3:1 \\
C's Share = \frac{1}{8}* 3200 \\
= 400
\end{aligned}
If you are confused how we multiplied 1/8, then please study ratio and proportion chapter, for small information, it is the C ratio divided by total ratio.
2. A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it
- 40 days
- 35 days
- 30 days
- 25 days
Answer: Option C
Explanation:
Suppose B takes x dáys to do the work.
As per question A will take
\begin{aligned}
2* \frac{3}{4} * x = \frac{3x}{2}days
\end{aligned}
(A+B)s 1 days work= 1/18
1/x + 2/3x = 1/18 or x = 30 days
3. A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in
- \begin{aligned} 13\frac{1}{4} \end{aligned}
- \begin{aligned} 13\frac{1}{2} \end{aligned}
- \begin{aligned} 13\frac{3}{4} \end{aligned}
- \begin{aligned} 13\frac{4}{4} \end{aligned}
Answer: Option C
Explanation:
A's 1 day work = 1/16
B's 1 day work = 1/12
As they are working on alternate day's
So their 2 days work = (1/16)+(1/12)
= 7/48
[here is a small technique, Total work done will be 1, right, then multiply numerator till denominator, as 7*6 = 42, 7*7 = 49, as 7*7 is more than 48, so we will consider 7*6, means 6 pairs ]
Work done in 6 pairs = 6*(7/48) = 7/8
Remaining work = 1-7/8 = 1/8
On 13th day it will A turn,
then remaining work = (1/8)-(1/16) = 1/16
On 14th day it is B turn,
1/12 work done by B in 1 day
1/16 work will be done in (12*1/16) = 3/4 day
So total days =
\begin{aligned} 13\frac{3}{4} \end{aligned}
It may be a bit typical question, but if are not getting it in first try then give it a second try. Even not, then comment for explanation for this. We will be happy to help you.
4. A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
- 4 days
- 5 days
- 6 days
- 7 days
Answer: Option C
Explanation:
(A+B)'s 1 day work = 1/4
A's 1 day work = 1/12
B's 1 day work =
\begin{aligned}
\left( \frac{1}{4} - \frac{1}{12} \right) \\
= \frac{3-1}{12} \\
= \frac{1}{6} \\
\end{aligned}
So B alone can complete the work in 6 days
5. A can do a job in 16 days, B can do same job in 12 days. With the help of C they did the job in 4 days. C alone can do the same job in how many days ?
- \begin{aligned} 6\frac{1}{2}days \end{aligned}
- \begin{aligned} 7\frac{1}{2}days \end{aligned}
- \begin{aligned} 8\frac{3}{5}days \end{aligned}
- \begin{aligned} 9\frac{3}{5}days \end{aligned}
Answer: Option D
Explanation:
In this question we having, A's work, B's work and A+B+C work. We need to calculate C's work.
We can do it by,
(A+B+C)'s work - (A's work + B's work).
Let's solve it now:
C's 1 day work =
\begin{aligned}
\frac{1}{4}- \left(\frac{1}{16} +\frac{1}{12} \right) \\
=\left(\frac{1}{4} - \frac{7}{48} \right) \\
= \frac{5}{48}
\end{aligned}
So C can alone finish the job in 48/5 days,
Which is =
\begin{aligned} 9\frac{3}{5}days \end{aligned}
Thanks ! Your comment will be approved shortly !
- Copyright 2014 - All rights reserved
- Terms Of Use & Privacy Policy
- Contact Us
- Copyright