Question Detail

A can do a certain job in 25 days which B alone can do in 20 days. A started the work and was joined by B after 10 days. The number of days taken in completing the wotk were ?

  • \begin{aligned} 14\frac{2}{3}kmph \end{aligned}
  • \begin{aligned} 15\frac{2}{3}kmph \end{aligned}
  • \begin{aligned} 16\frac{2}{3}kmph \end{aligned}
  • \begin{aligned} 17\frac{2}{3}kmph \end{aligned}
Similar Questions :

1. A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in

  • \begin{aligned} 13\frac{1}{4} \end{aligned}
  • \begin{aligned} 13\frac{1}{2} \end{aligned}
  • \begin{aligned} 13\frac{3}{4} \end{aligned}
  • \begin{aligned} 13\frac{4}{4} \end{aligned}

2. A can finish a work in 18 days and B can do same work in half the time taken by A. then working together, what part of same work they can finish in a day

  • 1\5
  • 1\6
  • 1\7
  • 1\8

3. A tyre has two punctures. The first puncture alone would have made the tyre flat in 9 minutes and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how long does it take both the punctures together to make it flat ?

  • \begin{aligned} 3\frac{1}{5} min \end{aligned}
  • \begin{aligned} 3\frac{2}{5} min \end{aligned}
  • \begin{aligned} 3\frac{3}{5} min \end{aligned}
  • \begin{aligned} 3\frac{4}{5} min \end{aligned}

4. A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days

5. A man can do a piece of work in 5 days, but with the help of his son he can do it in 3 days. In what time can the son do it alone ?

  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 5\frac{1}{2}days \end{aligned}
  • \begin{aligned} 4\frac{1}{2}days \end{aligned}
Read more from - Time and Work Questions Answers