Question Detail

A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days
Similar Questions :

1. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?

  • 30 days
  • 40 days
  • 50 days
  • 60 days

2. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C

  • Rs. 300
  • Rs. 400
  • Rs. 500
  • Rs. 600

3. A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ?

  • 3 days
  • 4 days
  • 5 days
  • 6 days

4. A can do a certain job in 25 days which B alone can do in 20 days. A started the work and was joined by B after 10 days. The number of days taken in completing the wotk were ?

  • \begin{aligned} 14\frac{2}{3}kmph \end{aligned}
  • \begin{aligned} 15\frac{2}{3}kmph \end{aligned}
  • \begin{aligned} 16\frac{2}{3}kmph \end{aligned}
  • \begin{aligned} 17\frac{2}{3}kmph \end{aligned}

5. 5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio

  • 1:2
  • 1:3
  • 2:1
  • 2:3
Read more from - Time and Work Questions Answers