Question Detail

A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days
Similar Questions :

1. A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in

  • 5 days
  • 6 days
  • 7.5 days
  • 8.5 days

2. To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take

  • 24 days
  • 16 days
  • 12 days
  • 8 days

3. A can do a job in 16 days, B can do same job in 12 days. With the help of C they did the job in 4 days. C alone can do the same job in how many days ?

  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 8\frac{3}{5}days \end{aligned}
  • \begin{aligned} 9\frac{3}{5}days \end{aligned}

4. A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days

5. 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?

  • 6 days
  • 7 days
  • 8 days
  • 9 days
Read more from - Time and Work Questions Answers