Question Detail

A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days
Similar Questions :

1. A man can do a piece of work in 5 days, but with the help of his son he can do it in 3 days. In what time can the son do it alone ?

  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 5\frac{1}{2}days \end{aligned}
  • \begin{aligned} 4\frac{1}{2}days \end{aligned}

2. A does a work in 10 days and B does the same work in 15 days. In how many days they together will do the same work ?

  • 5 days
  • 6 days
  • 7 days
  • 8 days

3. A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it

  • 40 days
  • 35 days
  • 30 days
  • 25 days

4. 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?

  • 6 days
  • 7 days
  • 8 days
  • 9 days

5. A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in

  • 5 days
  • 6 days
  • 7.5 days
  • 8.5 days
Read more from - Time and Work Questions Answers