- Home
- Quantitative
- English
- Reasoning
- IT Officer
- Programming
-
Computer
- Computer Awareness Questions Answers - Set 1
- Computer Awareness Questions Answers - Set 2
- Important Abbreviations Computer Awareness Questions Answers
- Important File Extensions Questions Answers
- Computer System Architecture Questions Answers
- MS Office Questions Answers
- MS Excel Questions Answers
- MS PowerPoint Questions Answers
-
GK
- Geography Questions Answers
- Indian History Questions Answers
- World History Questions Answers
- Indian Economy Questions Answers
- Indian Polity and Constitution
- Physics Questions Answers
- Chemistry Questions Answers
- Biology Questions Answers
- First In India
- First In World
- Longest and Largest
- Books and Authors
- Important Days of year
- Countries and Capitals
- Inventions and Inventors
-
Current Affairs
- Current Affairs
- Current Affairs 2018
- Current Affairs 2018 - 2019 PDF
- Current Affairs August 2019
- Current Affairs July 2019
- Current Affairs June 2019
- Current Affairs May 2019
- Current Affairs April 2019
- Current Affairs March 2019
- Current Affairs February 2019
- Current Affairs January 2019
- Current Affairs December 2018
- Current Affairs November 2018
- Current Affairs October 2018
- Current Affairs September 2018
- Govt Jobs
- Exams
- Online Quiz
- You are here
- Home
- Quantitative Aptitude
- Arithmetic Aptitude Questions Answers
- Time and Work Questions Answers
- Aptitude Question
- Current Affairs 2019
- Current Affairs 2018
- Current Affairs December 2018
- Current Affairs November 2018
- Current Affairs October 2018
- Current Affairs September 2018
- Current Affairs August 2018
- Current Affairs July 2018
- Current Affairs June 2018
- Current Affairs May 2018
- Current Affairs April 2018
- Current Affairs March 2018
- Current Affairs February 2018
- Current Affairs January 2018
- Current Affairs 2018
- Current Affairs PDF
- Current Affairs PDF Download
- Current Affairs July 2019 PDF
- Current Affairs June 2019 PDF
- Current Affairs May 2019 PDF
- Current Affairs April 2019 PDF
- Current Affairs March 2019 PDF
- Current Affairs February 2019 PDF
- Current Affairs January 2019 PDF
- Current Affairs December 2018 PDF
- Current Affairs November 2018 PDF
- Current Affairs October 2018 PDF
- Current Affairs September 2018 PDF
- Current Affairs August 2018 PDF
- Current Affairs July 2018 PDF
- Current Affairs June 2018 PDF
- Current Affairs May 2018 PDF
- Current Affairs April 2018 PDF
- Current Affairs March 2018 PDF
- Current Affairs February 2018 PDF
- Current Affairs January 2018 PDF
Question Detail
A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
- 4 days
- 5 days
- 6 days
- 7 days
Answer: Option C
Explanation:
(A+B)'s 1 day work = 1/4
A's 1 day work = 1/12
B's 1 day work =
\begin{aligned}
\left( \frac{1}{4} - \frac{1}{12} \right) \\
= \frac{3-1}{12} \\
= \frac{1}{6} \\
\end{aligned}
So B alone can complete the work in 6 days
1. To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take
- 24 days
- 16 days
- 12 days
- 8 days
Answer: Option D
Explanation:
A+B 1 day work = 1/8
B+C 1 day work = 1/12
A+B+C 1 day work = 1/6
We can get A work by (A+B+C)-(B+C)
And C by (A+B+C)-(A+B)
So A 1 day work =
\begin{aligned}
\frac{1}{6}- \frac{1}{12} \\
= \frac{1}{12}
\end{aligned}
Similarly C 1 day work =
\begin{aligned}
\frac{1}{6}- \frac{1}{8} \\
= \frac{4-3}{24} \\
= \frac{1}{24}
\end{aligned}
So A and C 1 day work =
\begin{aligned}
\frac{1}{12} + \frac{1}{24} \\
= \frac{3}{24} \\
= \frac{1}{8}
\end{aligned}
So A and C can together do this work in 8 days
2. A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in
- \begin{aligned} 13\frac{1}{4} \end{aligned}
- \begin{aligned} 13\frac{1}{2} \end{aligned}
- \begin{aligned} 13\frac{3}{4} \end{aligned}
- \begin{aligned} 13\frac{4}{4} \end{aligned}
Answer: Option C
Explanation:
A's 1 day work = 1/16
B's 1 day work = 1/12
As they are working on alternate day's
So their 2 days work = (1/16)+(1/12)
= 7/48
[here is a small technique, Total work done will be 1, right, then multiply numerator till denominator, as 7*6 = 42, 7*7 = 49, as 7*7 is more than 48, so we will consider 7*6, means 6 pairs ]
Work done in 6 pairs = 6*(7/48) = 7/8
Remaining work = 1-7/8 = 1/8
On 13th day it will A turn,
then remaining work = (1/8)-(1/16) = 1/16
On 14th day it is B turn,
1/12 work done by B in 1 day
1/16 work will be done in (12*1/16) = 3/4 day
So total days =
\begin{aligned} 13\frac{3}{4} \end{aligned}
It may be a bit typical question, but if are not getting it in first try then give it a second try. Even not, then comment for explanation for this. We will be happy to help you.
3. 5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio
- 1:2
- 1:3
- 2:1
- 2:3
Answer: Option C
Explanation:
Let 1 man 1 day work = x
1 boy 1 day work = y
then 5x + 2y = 4(x+y)
=> x = 2y
=> x/y = 2/1
=> x:y = 2:1
4. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C
- Rs. 300
- Rs. 400
- Rs. 500
- Rs. 600
Answer: Option B
Explanation:
C's 1 day's work =
\begin{aligned}
\frac{1}{3}- \left(\frac{1}{6} +\frac{1}{8} \right) \\
=\left(\frac{1}{3} - \frac{7}{24} \right) \\
= \frac{1}{24} \\
A:B:C = \frac{1}{6}:\frac{1}{8}:\frac{1}{24} \\
= 4:3:1 \\
C's Share = \frac{1}{8}* 3200 \\
= 400
\end{aligned}
If you are confused how we multiplied 1/8, then please study ratio and proportion chapter, for small information, it is the C ratio divided by total ratio.
5. A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
- \begin{aligned} 35\frac{1}{2} \end{aligned}
- \begin{aligned} 36\frac{1}{2} \end{aligned}
- \begin{aligned} 37\frac{1}{2} \end{aligned}
- \begin{aligned} 38\frac{1}{2} \end{aligned}
Answer: Option C
Explanation:
Work done by A in 20 days = 80/100 = 8/10 = 4/5
Work done by A in 1 day = (4/5) / 20 = 4/100 = 1/25 --- (1)
Work done by A and B in 3 days = 20/100 = 1/5 (Because remaining 20% is done in 3 days by A and B)
Work done by A and B in 1 day = 1/15 ---(2)
Work done by B in 1 day = 1/15 – 1/25 = 2/75
=> B can complete the work in 75/2 days = 37 (1/2) days