Question Detail
5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio
- 1:2
- 1:3
- 2:1
- 2:3
Answer: Option C
Explanation:
Let 1 man 1 day work = x
1 boy 1 day work = y
then 5x + 2y = 4(x+y)
=> x = 2y
=> x/y = 2/1
=> x:y = 2:1
1. A man can do a piece of work in 5 days, but with the help of his son he can do it in 3 days. In what time can the son do it alone ?
- \begin{aligned} 7\frac{1}{2}days \end{aligned}
- \begin{aligned} 6\frac{1}{2}days \end{aligned}
- \begin{aligned} 5\frac{1}{2}days \end{aligned}
- \begin{aligned} 4\frac{1}{2}days \end{aligned}
Answer: Option A
Explanation:
In this type of question, where we have one person work and together work done. Then we can easily get the other person work just by subtracting them. As,
Son's one day work =
\begin{aligned}
\left(\frac{1}{3}-\frac{1}{5} \right) \\
=\left(\frac{5-3}{15} \right) \\
= \frac{2}{15}
\end{aligned}
So son will do whole work in 15/2 days
which is =
\begin{aligned} 7\frac{1}{2}days \end{aligned}
2. A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. In how many hours B can complete the work ?
- 10 hours
- 12 hours
- 16 hours
- 18 hours
Answer: Option B
Explanation:
Work done by A in 1 hour = 1/4
Work done by B and C in 1 hour = 1/3
Work done by A and C in 1 hour = 1/2
Work done by A,B and C in 1 hour = (1/4)+(1/3) = 7/12
Work done by B in 1 hour = (7/12)–(1/2) = 1/12
=> B alone can complete the work in 12 hour
3. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C
- Rs. 300
- Rs. 400
- Rs. 500
- Rs. 600
Answer: Option B
Explanation:
C's 1 day's work =
\begin{aligned}
\frac{1}{3}- \left(\frac{1}{6} +\frac{1}{8} \right) \\
=\left(\frac{1}{3} - \frac{7}{24} \right) \\
= \frac{1}{24} \\
A:B:C = \frac{1}{6}:\frac{1}{8}:\frac{1}{24} \\
= 4:3:1 \\
C's Share = \frac{1}{8}* 3200 \\
= 400
\end{aligned}
If you are confused how we multiplied 1/8, then please study ratio and proportion chapter, for small information, it is the C ratio divided by total ratio.
4. To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take
- 24 days
- 16 days
- 12 days
- 8 days
Answer: Option D
Explanation:
A+B 1 day work = 1/8
B+C 1 day work = 1/12
A+B+C 1 day work = 1/6
We can get A work by (A+B+C)-(B+C)
And C by (A+B+C)-(A+B)
So A 1 day work =
\begin{aligned}
\frac{1}{6}- \frac{1}{12} \\
= \frac{1}{12}
\end{aligned}
Similarly C 1 day work =
\begin{aligned}
\frac{1}{6}- \frac{1}{8} \\
= \frac{4-3}{24} \\
= \frac{1}{24}
\end{aligned}
So A and C 1 day work =
\begin{aligned}
\frac{1}{12} + \frac{1}{24} \\
= \frac{3}{24} \\
= \frac{1}{8}
\end{aligned}
So A and C can together do this work in 8 days
5. A tyre has two punctures. The first puncture alone would have made the tyre flat in 9 minutes and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how long does it take both the punctures together to make it flat ?
- \begin{aligned} 3\frac{1}{5} min \end{aligned}
- \begin{aligned} 3\frac{2}{5} min \end{aligned}
- \begin{aligned} 3\frac{3}{5} min \end{aligned}
- \begin{aligned} 3\frac{4}{5} min \end{aligned}
Answer: Option C
Explanation:
Do not be confused, Take this question same as that of work done question's. Like work done by 1st puncture in 1 minute and by second in 1 minute.
Lets Solve it:
1 minute work done by both the punctures =
\begin{aligned}
\left(\frac{1}{9}+\frac{1}{6} \right) \\
=\left(\frac{5}{18} \right) \\
\end{aligned}
So both punctures will make the type flat in
\begin{aligned}
\left(\frac{18}{5} \right)mins \\
= 3\frac{3}{5} mins
\end{aligned}