Question Detail

4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?

  • 30 days
  • 40 days
  • 50 days
  • 60 days
Similar Questions :

1. A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in

  • 5 days
  • 6 days
  • 7.5 days
  • 8.5 days

2. A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ?

  • 3 days
  • 4 days
  • 5 days
  • 6 days

3. A is twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work.

  • 27 days
  • 54 days
  • 56 days
  • 68 days

4. A man can do a piece of work in 5 days, but with the help of his son he can do it in 3 days. In what time can the son do it alone ?

  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 5\frac{1}{2}days \end{aligned}
  • \begin{aligned} 4\frac{1}{2}days \end{aligned}

5. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C

  • Rs. 300
  • Rs. 400
  • Rs. 500
  • Rs. 600
Read more from - Time and Work Questions Answers