36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work ?

  • 24 days
  • 28 days
  • 34 days
  • 35 days
Similar Questions :

1. If the price of 23 toys is 276, then what will the price of 12 toys ?

  • 144
  • 148
  • 156
  • 186

2. An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metre of cloth ?

  • 194 seconds
  • 195 seconds
  • 196 seconds
  • 197 seconds

3. A flagstaff 17.5 metre high casts a shadow of length 40.25 metre. The height of building, which casts a shadow of length 28.75 metre under similar conditions will be :

  • 12 metre
  • 12.5 metre
  • 13.5 metre
  • 14 metre

4. 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work ?

  • 24 days
  • 28 days
  • 34 days
  • 35 days

5. 4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat weavers in 8 days ?

  • 12
  • 14
  • 16
  • 18
Read more from - Chain Rule Questions Answers