Question Detail
36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work ?
- 24 days
- 28 days
- 34 days
- 35 days
Answer: Option A
Explanation:
Less Men, means more Days {Indirect Proportion}
Let the number of days be x
then,
27 : 36 :: 18 : x
[Please pay attention, we have written 27 : 36 rather than 36 : 27, in indirect proportion, if you get it then chain rule is clear to you :)]
\begin{aligned}
x = \frac{36*18}{27} \\
x = 24
\end{aligned}
So 24 days will be required to get work done by 27 men.